MBTA Halts Green Line for Nine-Day Signal Overhaul
Crews will install 16 miles of new cabling and upgrade seven stations during a full closure from November 7 to 15.
By Valentina Rojas ·

The MBTA will close all four branches of the Green Line for nine consecutive days starting November 7. The shutdown allows crews to work around the clock on signal replacements and station accessibility upgrades. The authority aims to complete this work in a single intensive window to minimize long-term service disruptions.
Crews will install 16 miles of new signaling cable and one mile of fiber optic cable within the central tunnel. This work builds on 56 miles of cable already installed during previous diversions. The goal is to replace a signal system that dates back to the late 1800s, when the first electric trolleys in North America began operating.
The new signal system is designed to improve train detection and manage congestion more effectively. It will also allow for more consistent train spacing, which supports higher service frequencies. The upgrade is compatible with the new Type 10 Green Line cars scheduled to enter passenger service next year.
Simultaneously, crews will advance accessibility improvements at seven above-ground stations on the C Branch. These stations, including Englewood Avenue, Dean Road, and Hawes Street, are currently inaccessible. The project aims to make every station on the C Branch compliant with accessibility standards.
Work on the C Branch includes installing underground conduit at Hawes Street and overhead catenary wire poles at Summit Avenue. Crews will also install platform edges, curbing, and lighting foundations. Structural steel for platform canopies will be added at the Brandon Hall and Fairbanks Street ramps. Existing inbound platforms at Hawes Street and Summit Avenue will be removed during this phase.
The MBTA is using the full track access to perform additional maintenance and upgrades. These tasks include replacing ties and ballast at Symphony station and installing security cameras at Park Street, Downtown Crossing, and Broadway. Crews will also upgrade radio systems and perform visual inspections of tunnel structures.
Riders should budget extra time for their commutes during the closure. For example, a trip from Cleveland Circle to Park Street via shuttle bus may take at least 25 minutes longer than usual. Free shuttle buses will connect Babcock Street to Back Bay on the B Branch and Kenmore to Back Bay on the D Branch. The Route 39 bus will replace E Branch service between Heath Street and Back Bay.
All shuttle buses will be accessible to riders with disabilities. Weekday service will use lift-equipped coach-style buses, while weekend service will use ramp-equipped, low-floor buses. Accessible van service will be available between North Station and Kenmore upon request. The Worcester Commuter Rail Line will also operate fare-free between South Station, Back Bay, and Lansdowne during this period.
The MBTA states that the two-phase approach to platform upgrades allows for immediate safety improvements while preserving a path for future changes. Current platforms are being built to an 8-inch height to accommodate the existing fleet. A future phase will add six inches to reach a 14-inch height for level boarding with Type 10 vehicles once the current fleet is retired.